MPC(23)06.06 CIL and Grant Funded Projects Report

Agendas & PapersFull Council Uploaded on January 12, 2023

MPC(23)06.06

Report on CIL and Ear Marked Resources (EMR) funded projects – January 2023

Background and summary

This report updates Full Council on the situation regarding CIL and EMR projects as at 31st December 2022. At this date the EMRs totalled £187,273 as follows:

EMR Title Total as at 31st Dec 2022 Total as at 31st Oct 2022 Total as at 31st Aug 2022 Total as at 30th June 2022 Total as at 28 Feb 2022 Original allocation Notes
CIL reserves £96,456.73 £111,928.73 £102,544.91 £128,164.91  

£133,519

 

N/A
EMR Melton Rd crossings project £35,755 £35,755 £35,755 £35,755  

£35,755

 

£40,000
EMR Landscaping & parking improvements £3,717.03 £56,077.47 £56,265 £51,265  

£49,000

 

£50,000 Additional £5k added July 2022
EMR Pavilion project £16,370.91 £47,263.38 £144,595.16 £189,943.85 £274,446 £220,000 Additional £75k added in March 2022

Additional £10k added July 2022

Additional £25k added Sept 2022

EMR Bins £1,822.88 £2,000 £2,000 £2,000  

£2,000

 

£2,000
EMR Divested land sinking fund £18,822.17 £18,998 £18,998 £18,998 £23,843 £30,000
Signage £1,130 £2,840 £2,840 £3,000 N/A £3,000
Total £174,074.72 £274,862.58 £362,998.07 £429,126.76 £518,563
Budget Risk EMR * £5,000 £5,000 £5,000 £5,000 £5,000
Hall Farm Road/SWT Events* £590 £690 £690 £690 N/A £3,633
Bequest EMR* £1,500 £1,500 £1,500 £1,500 N/A £1,500
Fete EMR* £849.34 £874.34 £874.34 £2,594.31 N/A £623.97
Pavilion Kit Out EMR* £5.30 £63.89 £1,185.96 N/A N/A £1,185.96 Agreed by FERM in June 2022. Established through fete
Deposits EMR** £100 Key deposit
1st Floor Rent Deposit** £5,153.64 Interest added in Dec 2022

* These EMRs are not funded by CIL. **These are deposits held by the Council and should not be treated in the same way as other Reserves.

CIL received and spent to date

Receipts to date (payments are usually made in April and October in each year):

2016 £4,720

2017 £75,172

2018 £3,652

2019 £245,651

2020 £183,667

2021 £106,600

2022 £18,097.63

TOTAL = £637,559.63

The appeal lodged by the developer of Deben Meadows was rejected. We hope to receive further CIL payments for this in 2023.

Expenditure to date:

2018/19 £2,324

2019/20 £8,554

2020/21 £11,243

2021/22 £89,652.46

2022/23 (to date) £351,710.91

TOTAL = £463,484.37

 In terms of spend deadlines, the earliest unspent tranches now date from April 2020, which needs to be spent by April 2025.

Projects completed and paid using CIL/EMR

  • Playing Field security CCTV system
  • Speed Indicator Devices x 3
  • Recreation Ground Car Park improvements
  • Land Divestment improvements/enhancements
  • Bredfield Bus Shelter – (No EMR created) – £2.4k in total but £700 funded by grant
  • Hall Farm Road play equipment installation and enhancements
  • Creation of car park and installation of bike racks in front of Winifred Fison House
  • SWT wildlife events x 3
  • Lighting of pathway to Pavilion (using solar lighting)
  • Access road to Pavilion
  • Yarmouth Road repeater roundels – funded partly by Cllr Nicoll
  • Quiet Lanes – two lanes designated and signs installed

 

Projects in Progress

  • Melton Road/Hill crossings – installed July 2022. Some money may remain on completion – awaiting final invoice.
  • Pavilion – in use from December 2022. Final snagging being undertaken.
  • Bredfield Road Feasibility Study – funded by grants from Cllrs Nicoll and Smith-Lyte
  • De-fib for Pavilion – funded through Cllr Smith-Lyte and bequest
  • Heavy duty gazebos – £1.5k allocated
  • Planting at car park near Winifred Fison House

Prioritised Projects

  • Beresford Drive play park – Highest priority – Recreation have agreed to hold a consultation day at Beresford Drive, similar to Hall Farm Road, on the 1st It was suggested to take place in the morning 10am-noon but afternoon may be more appropriate – the Hall Farm Road event was 2-4pm.
  • Recreation Ground Play Park – High priority
  • Recreation Ground Bike Track – High priority – Recreation have agreed to gauge interest of residents initially through posters in the woods and comm
  • Bike racks at the Pavilion – High priority – will be installed after the landscaping has taken place.
  • MUGA replacement – Medium priority
  • Playpark Fencing – Medium priority
  • Tennis Court Resurfacing – Low priority
  • Solar Panels – Low priority
  • EV Charging Points – Low priority

Additional Requests

A resident has asked if a bench can be sited along Melton Road to give somewhere for elderly/less able pedestrians to rest if they walk along Melton Road. The office has made enquiries about a suitable location as MPC does not own any land on Melton Road that would be appropriate. Cllr Nicoll may be able to part fund a bench but Councillors are asked if they are happy to fund the remainder (up to £500) if permission is granted.

Recommendations

Members are asked to:

  • Note and comment on the report
  • Agree to funding a new bench

 

 

Pip Alder

Clerk and Executive Officer to the Council

January 2023