RECORD OF DECISIONS DELEGATED TO THE CLERK TO THE COUNCIL IN ACCORDANCE WITH THE REQUIREMENTS OF THE OPENNESS OF LOCAL GOVERNMENT BODIES REGULATIONS 2014

 

DECISION NUMBER

 

18
DATE(S) OF DECISION(S)

 

1.     22nd February 2023

2.     20th February 2023

 

OPTIONS CONSIDERED

 

 

 

 

1.     Change of electricity supplier at the Pavilion

The current contract with EDF ends in April 2023. Alternative quotes were sought from EDF, Octopus Energy and British Gas Lite.

 

Supplier EDF (current rate) EDF (renewal) British Gas Lite British Gas Lite Octopus
Tariff Term ends April 2023 1 year fix 1 year fix 2 year fix 1 year fix
Day Rate/kw 38.2p 45.21p 38.72p 37.53p 36.03p
Night Rate/kw 34.8p 34.35p 27.72p 26.23p 25.88p
Standing Charge/day 25p 60p 40p 42p 38p
Estimated annual bill £822.09 £1,034.19 £831.81 £843.39 £777.45
SEG payment/kw

(solar power export payment)

N/A 5.6p (customer)

3p (non customer)

6.4p 6.4p 15p (customer)

4.1p (non customer)

Octopus Energy has been selected on the grounds of cost, green credentials and their high SEG payment price. The new contract will start in April 2023.

 

 

2.     Renewal of greenspace management contract

The three-year contract with our greenspace management company was up for renewal at the end of this financial year. Alternative providers were approached but their quotes were far higher than the current provider. We have agreed a price of £5,414.01 for the next financial year based on the same terms and schedule as the previous agreement. This is an increase from £4,798 (March 2020).

MEMBER CONFLICT OF INTEREST DECLARED? No