Some survey works will be carried out in the coming weeks as part of the railway infrastructure for Sizewell C across the region.
Surveys will be carried out at Melton Level Crossing on the following dates:
Location | Dates | Time | Planned Works |
Melton Level Crossing Phase 1 | 28/08/24 – 28/08/24 | 22:00 – 06:00 | SZC Rail Scheme – Non-Intrusive Ground Investigation Surveys |
Melton Level Crossing Phase 2 | 09/09/24 – 12/09/24 | 22:00 – 06:00 | SZC Rail Scheme – Intrusive Ground Investigation Surveys |
These works can only take place when there are no trains running.
The ground investigation surveys will be conducted by Balfour Beaty. These works will include use of equipment to identify utility services on and within the level crossing. This will involve coring holes using electric and hydraulic corers. We apologise for any disturbance caused.
As a result of these works, there will be road closures with diversions in place. A map of the route is attached and can be found online at https://one.network
If you have any questions, please do contact the helpline 0800 197 6102 or email info@sizewellc.com