Sizewell C – Application for Development Consent Order Accepted

The application for Development Consent Order has been accepted by the Planning Inspectorate on 24 June 2020. The Parish Council has been sent details of the planning application for Sizewell C.  The application has been accepted by the Planning Inspectorate and now the Examining Authority will be appointed.

The Parish Council, other consultees and the public may now make representations about the Sizewell C application by using the Planning Inspectorate’s Registration & Relevant Representation Form for this application from the 8th July to 30th September.  Any Registration & Relevant Representation Form must be received by the Planning Inspectorate by 30 September 2020.

All of the application documentation that has been submitted by Sizewell C Co. to the Planning Inspectorate (PINS) can be viewed at https://sizewellcdco.co.uk/

If you would prefer to view a hard copy, a mobile DCO library will be visiting various locations in East Suffolk throughout July and August. Book an appointment on 0800 197 6102 to reserve
your viewing slot.

Leiston-cum-Sizewell – 13/14/15 July
Theberton – 16/17 July
Middleton – 20/21 July
Yoxford – 22/23 July
Kelsale-cum-Carlton – 24 July
Darsham – 27/28 July
Wickham Market – 29/30 July
Hacheston – 31 July
Levington – 3/4 August
Stratford St Andrew – 5/6 August
Woodbridge – 7 August
Ipswich – 10 August
Lowestoft – 11 August

Letter from 54 Town & Parish Councils regarding Sizewell C

In response to a letter to EDF (dated 9 April) from Suffolk County Council and East Suffolk Council concerning its Development Consent Order (DCO) application for Sizewell C, a joint letter from 54 Town and Parish Councils, including Melton Parish Council, was sent to the Council leaders on 11 May. The key message was that examination of the planning application must be in public and not be digital-only. A copy of the letter is available to read as a PDF:

Town and Parish Council Letter – 11 May 2020

Sizewell C – Application for a Development Consent Order

On 3 April 2020, EDF wrote to Parish Councils confirming its decision to defer, by a few weeks, the submission of its application for a Development Consent Order (DCO) to build Sizewell C. EDF says that this will allow everyone more time to read the documents through the summer months and then register their interest and submit their views for the public examination phase of the DCO process. EDF is liaising with the Planning Inspectorate to discuss how normal arrangements can be flexed so that communities are not disadvantaged by the current difficult circumstances.

Sizewell C

EDF Energy will now be running a Stage 4 public consultation exercise starting on 18 July 2019 and running until 27 September 2019. This will include a drop-in session at Woodbridge Community Hall on 26 July from 2pm to 8pm.

Sizewell C Stage 3 public consultation began on 4 January 2019 and ran to 29 March 2019. The new station would be located to the north of Sizewell B, and would have two reactors capable of generating enough low carbon electricity to supply around 6 million homes for 60 years.

Melton Parish Council’s Responses to Consultations:

Stage 2 Response

Stage 3 Response